Working With Utility Companies Reference

Why this matters

Service techs work with utility companies regularly - new connections, service upgrades, emergencies, restoration. The tech who understands utility processes coordinates effectively + helps customers navigate. This is the field card.

Utility types

Electric utility:

  • Local provider (PG&E, Duke, Edison, etc.)
  • Distribution within local area
  • Service from pole / underground to meter
  • Customer side: meter to panel + circuits

Gas utility:

  • Local provider (often same OR different than electric)
  • Distribution mains
  • Service to meter
  • Customer side: meter to appliances

Water utility:

  • Municipal usually
  • Sometimes private
  • Treatment + distribution
  • Customer side: meter to plumbing

Wastewater (sewer):

  • Often municipal water
  • Collection mains
  • Customer side: house plumbing to sewer connection

Telecom:

  • Sometimes regulated as utility
  • Phone, cable, fiber

What's "utility side" vs "customer side"

Demarcation point = where customer's responsibility starts.

Electric:

  • Utility owns: pole, transformer, drop wire to meter
  • Customer owns: from meter to panel + everything downstream
  • Meter itself: utility owns (some areas, customer pays for)

Gas:

  • Utility owns: main + service line to meter
  • Customer owns: from meter to all appliances
  • Some areas: customer owns service line from main

Water:

  • Utility owns: main + sometimes to property line
  • Customer owns: from property line (or meter) to fixtures
  • Varies by jurisdiction

Each side responsible for repairs / maintenance / safety.

Common utility interactions

Service entrance work:

  • Replacing panel
  • Service upgrade (100A to 200A)
  • Coordinating with utility (sometimes utility must disconnect)

New service:

  • New construction
  • Major addition
  • Detached structure with separate meter

Gas main extension:

  • Customer wants gas (none nearby)
  • Utility extends main (sometimes at cost)
  • Customer extends service

Water main connection:

  • New house
  • Replace deteriorated service line
  • Permits + utility coordination

Pre-work utility coordination

For service entrance work:

  1. Customer contacts utility (call before dig OR service request)
  2. Utility schedules disconnect OR site visit
  3. Permit obtained (electrical typically)
  4. Disconnect day:
  • Utility removes meter / disconnects
  • You do work
  • Same-day OR overnight
  1. Reconnect:
  • Inspection passes
  • Utility reconnects
  1. Customer notification of restoration

Coordinate timing carefully; customer without power = significant inconvenience.

Permit + utility interaction

For utility-affecting work:

  • Permit typically required
  • Inspector approves work
  • Utility reconnects after inspection
  • Don't bypass utility approval

Service capacity increase

Customer adds load:

  • EV charger (significant)
  • New addition
  • Pool / hot tub
  • HVAC upgrade

If existing service inadequate:

  • Service upgrade required
  • 100A โ†’ 150A โ†’ 200A โ†’ 400A
  • Utility may upgrade meter base + transformer
  • Customer pays for service entry conductors

Cost responsibility

Generally:

  • Utility provides up to meter
  • Customer pays meter onward
  • Service upgrades: customer pays
  • Sometimes utility absorbs some costs (depends on customer's contribution)

Verify with utility for specific situation.

Emergency calls

Gas leak:

  • Customer calls 911 + utility immediately
  • Utility shuts off main if needed
  • Repair coordinated
  • Customer evacuates until safe

Water main break:

  • Utility responds
  • Shuts off main
  • Coordinates repair
  • Customer affected but utility primary

Electrical emergency:

  • Downed line: utility emergency
  • Customer's panel: customer's tech / electrician

When you need utility involvement

Service entrance:

  • Pull meter
  • Disconnect service
  • Reconnect after work

Underground utility location:

  • 811 (Common Ground Alliance)
  • Free service
  • Marks gas, electric, water, sewer, communications
  • Allow 2-3 business days

Permit OR inspection involving utility:

  • Some work requires utility sign-off
  • New service connection
  • Capacity upgrade

811 (Call Before You Dig)

Federal law (most areas):

  • Notify utility before excavating
  • Free
  • Online OR phone
  • Utilities mark within 2-3 business days

Mark colors (APWA standard):

  • Red: Electric power
  • Yellow: Gas, oil, steam, petroleum
  • Orange: Communications, alarm
  • Blue: Potable water
  • Green: Sewer + drain
  • Purple: Reclaimed water, irrigation
  • Pink: Temporary survey markings
  • White: Proposed excavation

Mark validity: typically 14 days (varies by state).

Damages to utility

If you damage utility line:

  • Stop work IMMEDIATELY
  • 911 if leak / live wire
  • Notify utility
  • Mark area as hazardous
  • Cost of repair often borne by you (insurance)

Properly called 811 + damage occurred during scope = utility may absorb cost (state law varies).

Customer educational opportunities

Customer often unclear:

  • "Who's responsible if pipe breaks under my driveway?"
  • "Who pays for service upgrade?"
  • "Why can't I just hook up?"

Explain:

  • Side of meter responsibility
  • Permit + inspection requirements
  • Why utility involvement
  • Timeline

Slow utility response

Utility's process may be slow:

  • 2-3 weeks for service upgrade
  • Weeks for new connection
  • Customer impatient

Set expectation:

  • Communicate utility's role + timeline
  • Don't promise faster than utility can
  • Customer's frustration directed at utility (where appropriate)

When utility is wrong

Sometimes utility:

  • Marks incorrectly (811 mark wrong location)
  • Damages customer's property
  • Misses scheduled connection
  • Quotes wrong information

Process:

  • Document
  • Customer files complaint
  • Sometimes regulatory commission involvement
  • Customer's recourse (you can't fix utility)

Working safely near utilities

Overhead lines (per overhead clearance article):

  • 10 ft minimum from anything
  • Higher voltage = more

Underground:

  • 811 first
  • Pothole carefully near marks
  • Hand-dig within 24" of marked utility

Service lines:

  • Don't dig blindly anywhere near suspected utility

Utility company structure

For your reference:

  • Customer service: general inquiries, billing
  • Service dispatch: connection work, emergencies
  • Engineering: design work, large customer projects
  • Construction: actual work crews
  • Meter reading + billing: customer-side
  • Emergency dispatch: 24/7

Knowing who to call = faster resolution.

Specific scenarios

Customer wants service entrance moved:

  • Significant project
  • Utility involvement extensive
  • Customer pays
  • Multi-step coordination

Customer's underground service deteriorated:

  • Customer pays for replacement (usually)
  • Utility may have to be involved
  • Significant disruption

References

  • 811 (Common Ground Alliance)
  • State utility commission regulations
  • NEC + NFPA standards for utility interconnection
  • Utility company tariffs + service standards
  • Manuall internal: Underground Utility Clearances, Overhead Utility Clearances