Asphalt Shingle Roof Replacement SOP
Purpose
Standardize the full tear-off + replacement of an asphalt shingle roof. The biggest job most residential roofers do; quality variation here drives 90% of warranty claims + reputation issues.
Scope
Single-family residential, 1-2 story, asphalt shingle to asphalt shingle. Excludes commercial, tile, slate, metal, or roof + structure complete rebuilds.
Prerequisites
- Permit pulled (most jurisdictions require)
- HOA approval (if applicable)
- Materials staged on-site or delivery scheduled
- Crew of 3-5 trained roofers
- Weather window: 2-3 dry days minimum, temp 45-95°F ideal
- Dumpster delivered for tear-off debris
- Plywood + tarps on hand for emergency cover
Materials checklist
- Shingles (per spec, +10% waste factor)
- Underlayment (synthetic preferred; felt acceptable)
- Ice + water shield (eaves + valleys per code)
- Drip edge (aluminum or steel)
- Starter strip (or use cut shingles)
- Ridge cap shingles (or use field shingles)
- Roofing nails (1.25" galvanized, ring-shank)
- Pipe boots (replace; never reuse)
- Step flashing (against walls)
- Counter-flashing (chimney/wall transitions)
- Caulk (poly urethane roofing grade)
Procedure
Day 1 morning - Setup (1 hour)
- Protect landscaping with tarps
- Stage dumpster as close to house as access permits
- Set up edge protection (debris catcher) if needed
- Brief crew: assignments, safety, plan for the day
- Cover AC condensers + skylights
Day 1 - Tear-off (3-6 hours, varies by roof size)
- Start at ridge, work down
- Remove shingles + underlayment to deck
- Remove drip edge, pipe boots, flashings
- Pull all nails (or hammer flush; loose nails puncture new underlayment)
- Inspect decking - soft / rotten / delaminated sheets get replaced (note for change order)
- Clean roof completely - magnetic sweeper around house twice
Day 1 afternoon - Decking + dry-in (2-4 hours)
- Replace any damaged decking with 1/2"+ plywood / OSB
- Install ice + water shield on eaves (per local code; typically 24" past warm wall OR 3' minimum)
- Install ice + water shield in valleys (36" wide centered)
- Install drip edge at eaves (under ice + water shield is acceptable; over is common)
- Roll out underlayment, working ridge-to-eave with 4" overlaps
- Install drip edge at rakes (over underlayment)
- Cap-nail underlayment every 8-12" along laps
If weather threatens, complete dry-in BEFORE end of Day 1.
Day 2 - Shingles + flashing (4-8 hours)
- Snap chalk lines for first course
- Install starter strip at eaves (factory adhesive toward eave)
- Install first course flush with starter
- Continue up roof maintaining offset pattern per manufacturer (typically 5-6" stagger)
- Nail per spec: 4 nails per shingle (6 on steep slopes / high-wind zones)
- Nail placement: in the nail strip ONLY (above sealant, below cutout); never high-nailed
- Install pipe boots, step flashing, counter-flashing as you reach them
- At valleys: closed-cut or open-metal per spec; closed-cut most common
Day 2 - Ridge + cleanup (1-2 hours)
- Install ridge vent (if specified) OR ridge cap shingles
- Cap shingles: hand-cut from 3-tab or use pre-made
- Final magnetic sweep around house
- Walk roof inspecting nail strikes (raised nails get reseated)
- Clean gutters of debris
- Photo the completed roof
Day 3 (if needed) - Punch list + customer walkthrough
- Customer walkthrough - point out new flashings, vents
- Provide manufacturer warranty registration
- Provide your labor warranty in writing
- Final invoice + payment
Acceptance Criteria
- All shingles laid to manufacturer pattern + spec
- Nail count + placement per spec
- All penetrations re-flashed (no reuse)
- Ice + water shield at eaves + valleys per code
- Roof passes "no daylight visible from attic" check
- Site clean - no nails, no debris in landscaping
- Customer signs off on punch list
Common pitfalls
- Reusing pipe boots: leak in 2-3 years; always replace
- High-nailing: nail above the strip - visible, voids warranty, blows off in wind
- Skimping on ice + water shield: code violation in cold climates; ice dams cause leaks
- No drip edge: water wicks under shingles at edges; rots fascia
- Inadequate ventilation: shortens shingle life by 5-10 years
- Walking on hot shingles: damages granule layer; voids manufacturer warranty
- Skipping decking inspection: hidden rot becomes a callback
Safety notes
- Fall protection: harness above 6 ft is OSHA required
- Two ladders set + secured per house side
- No work in wind > 25 mph or wet conditions
- Hydration breaks every 60-90 min in heat
- One person on ground spotting at all times
The single biggest reroof-quality issue: NAIL PLACEMENT. Manufacturer spec is precise; the "nail strip" is the only correct location. High nails void warranty + cause wind blowoffs; low nails miss the previous course + tear out under wind load. Train every roofer to nail in the strip ONLY. A nail-placement audit on every job catches this before customer signoff.
References
- NRCA installation guidelines
- Local building code (IRC R905)
- Manufacturer installation instructions (binding warranty)
- Manuall internal: Residential Roof Inspection SOP, Asphalt Shingle Types + Ratings Reference