Whole-House Standby Generator Installation SOP

Purpose

Standardize installation of permanently-mounted whole-house standby generators. Combines electrical work, gas plumbing, foundation work, + system commissioning. Wrong install = generator that doesn't start when needed.

Scope

Residential standby generators (Generac, Kohler, Briggs & Stratton, Champion) 10-26kW range, natural gas or propane fueled. Excludes portable generators (different SOP) + commercial standby systems.

Prerequisites

  • Generator specified (sized + selected with customer)
  • Site preparation: concrete pad area cleared
  • Permits pulled: electrical + gas (sometimes building)
  • Generator delivered + uncrated
  • Tools: standard electrical kit, gas-line tools, masonry tools for pad
  • Crew: licensed electrician + plumber + helper (2-3 trade specialties)
  • 2-3 days for typical install

Pre-install survey + planning

Step 1: Site survey (during quote)

  1. Generator location:
  • 18 inches minimum from house exterior wall
  • 5 feet minimum from operable windows + doors
  • 3 feet from combustibles
  • Level area for concrete pad
  • Accessible for service (3 ft clearance all sides)
  1. Fuel source:
  • Natural gas: meter location, BTU capacity check
  • Propane: tank size needed, tank location
  1. Electrical:
  • Distance to main panel
  • Service amperage (200A typical for whole-house)
  • Existing transfer switch (replacing) or new install
  1. Permits required:
  • Electrical permit
  • Gas permit (sometimes plumbing permit)
  • Building permit if pad work

Procedure

Day 1 - Site prep + concrete pad (4-6 hours)

  1. Mark location with stakes
  2. Excavate to 6 inches deep
  3. Compact base
  4. Form + pour concrete pad (4 inches minimum thickness, typically 4×4 ft or larger)
  5. Embed conduits during pour for electrical + gas
  6. Cure 24+ hours before generator placement

Or use pre-fabricated composite pad - quicker but more $.

Day 1 afternoon - Run conduits + lines

  1. Underground conduit from generator to house service panel
  • 1-1/4" PVC minimum for the main service feeder
  • 3/4" PVC for control wiring
  • 18-24" deep trench
  1. Gas line from existing gas service (or new propane tank)
  • Size per generator BTU + run distance
  • Drip leg + shutoff at generator

Day 2 - Generator placement + connections (4-6 hours)

  1. Position generator on pad with crane or 4-person lift
  2. Anchor with concrete fasteners
  3. Connect gas line + perform pressure test
  4. Run electrical conductors from generator to transfer switch
  5. Install transfer switch (see: Transfer Switch Installation HowTo)
  6. Connect battery + battery charger
  7. Connect natural gas + open valve (test for leaks with detector)

Day 2-3 - Transfer switch + load wiring (4-6 hours)

  1. Install transfer switch beside main panel (in conduit-accessible location)
  2. Wire from generator output → transfer switch
  3. Wire from transfer switch → main panel (or sub-panels for partial load)
  4. Determine load priorities:
  • Whole-house: all circuits supported
  • Essential circuits: selected critical circuits
  1. Re-route branch circuits as needed

Day 3 - Commissioning + customer walkthrough (2-3 hours)

  1. Initial inspection:
  • All connections torqued to spec
  • Gas line pressure tested
  • Battery installed + charged
  • Oil + coolant levels verified
  1. Generator start test:
  • Manual start (with utility on)
  • Verify proper RPM + voltage
  • Verify frequency (60 Hz)
  1. Transfer switch test:
  • Simulate utility outage (open main breaker briefly)
  • Generator auto-starts within 20-30 seconds
  • Transfer switch transfers load
  • Generator runs steady
  1. Restore utility:
  • Close main breaker
  • Transfer switch returns to utility power
  • Generator continues running 1-2 min cooldown
  • Generator shuts off
  1. Auto-test:
  • Configure weekly self-test (typical: Tuesday morning, 5 minutes)
  1. Customer briefing:
  • Demonstrate operation
  • Explain auto-test schedule
  • Maintenance schedule (annual)
  • Battery replacement (every 2-3 years)
  • Provide all manuals + warranty info
  • Mobile app setup (most modern units)

Acceptance criteria

  • Generator anchored + level
  • All electrical connections torqued + inspected
  • Gas pressure tested (leak-free)
  • Transfer switch operational
  • Auto-start verified
  • Weekly self-test configured
  • Customer signoff on operation
  • Permits inspected + closed

Common pitfalls

  • Wrong placement: too close to house, blocked airflow, neighbor complaint about noise
  • Undersized gas line: generator starves for fuel at full load
  • Wrong transfer switch type: load mismatch (whole-house vs essential-only)
  • Skipped pressure test: gas leak hazard
  • Battery left disconnected: generator won't auto-start
  • Cooldown timer too short: generator overheats on shutdown
  • Auto-test scheduled during sleep hours: customer complaint
  • Not training customer: customer has no idea what's happening when it runs
  • Permit not closed: legal issue later

Sizing review (verify before install)

A whole-house generator should match home load. Common ratings:

  • 8-10 kW: small home, essential circuits only
  • 14-17 kW: medium home, most circuits + AC
  • 20-26 kW: large home, whole-house

Rule of thumb: 1.5-2 kW per 1,000 sq ft of conditioned space. Verify with full electrical load calculation.

Permits + inspections

  • Electrical permit: required in most jurisdictions
  • Gas permit: required
  • Building permit: sometimes for pad work
  • Air quality permit: required in some areas
  • HOA approval: confirm before scheduling work

Inspector visits typical:

  • Rough electrical (before sheetrock if interior conduit)
  • Final electrical (transfer switch operational)
  • Gas (pressure test + leak check)

Maintenance schedule to set up

  • Weekly: 5-minute auto-test (configured during install)
  • Monthly: customer visual inspection
  • Annually: locksmith service visit (oil change, filter, inspection)
  • Every 2-3 years: battery replacement
  • Every 200 hours of run time: deeper service (post-extended outage)

Customer follow-up

  • 30 days post-install: call to verify everything operating
  • 6 months: reminder for first annual service
  • Annual maintenance contracts: 60-80% conversion rate

NEVER install a standby generator without VERIFYING THE NATURAL GAS METER + LINE CAPACITY. A standard residential gas meter is sized for furnace + water heater + range. Adding a 20kW generator can exceed meter capacity, causing pressure drops that starve everything. ALWAYS check gas meter capacity rating + ensure adequate capacity (may require gas company meter upgrade - done FREE in most utilities). Missing this check means the customer's generator works in test, fails when AC is also running on a hot day.

References

  • Manufacturer installation manuals (Generac, Kohler, etc.) - legally binding
  • NEC Article 700 (Emergency Systems) + Article 702 (Optional Standby)
  • NFPA 70 + 110 + 37 + 54
  • IRC residential
  • Manuall internal: Transfer Switch Installation, Generator Sizing for Residential